# Sample: What a late PPAP really costs
- URL: https://redhillsqc.up.railway.app/posts/sample-what-a-late-ppap-really-costs/
- Published: 2026-08-25T16:25:03.000Z
- Updated: 2026-09-15T16:25:05.000Z
- Description: We treated a PPAP slip as a paperwork problem, and the recovery ended up costing more than the launch.
- Author: Daanish
- Tags: Lessons Learned

## What happened

A submission slipped by three weeks. The parts were good, the process was capable, and the only thing outstanding was a measurement systems study on a single characteristic. Everyone treated it as paperwork.

## What it actually cost

The customer would not approve production without a full submission, so the launch ran on a deviation. Under the deviation every shipment needed a signature, and the first shipment after a shift change went out without one.

- Two weeks of certified shipping.
- A customer audit that would not otherwise have happened.
- A supplier rating drop that took two quarters to recover.

## The lesson

Each PPAP element is evidence the customer uses to decide whether to trust the process. Treat an outstanding element as an open risk with a date on it, and escalate it on the same clock as a quality problem.

*This is a sample post. It is a Case Study filed under Lessons Learned, because being a Lesson is a flag on a Post and has no layout of its own. Delete it or replace it once there is real material to publish.*